Chandra completed its sixth year of successful scientific operations
      on 23 July 2005, with the spacecraft and science instruments
      continuing to perform in an outstanding manner. The 6-year
      milestone was celebrated with the 6 Years of Science with
      Chandra symposium held in Cambridge in November. The quality and
      depth of the results presented at the symposium spoke to the
      impact that Chandra is having on our field. Of particular note
      was the number of papers that involved multiwavelength data from
      Chandra, Spitzer and Hubble - NASA’s three Great
      Observatories. As we head into the 7th year of observations, it
      is not surprising that over-subscription rates remain very high
      for the Chandra user research programs, including the General
      Observer, archive research, and Directors Discretionary Time
      programs, and the Chandra Fellows program, which is now in its
      8th cycle. As the mission progresses, it is clear just how
      important a role Chandra plays as NASA’s prime X-ray astronomy
      asset.
   
  The staff of the CXC worked hard during the last year to
    maintain the high standards
	met throughout the mission so far. Of particular note were the
	increasing temperatures measured in all spacecraft subsystems
	as the passive thermal insulation degrades due to continued
	exposure to radiation. The rising temperature has resulted in
	increasingly more complex mission planning constraints and has
	started to have a measurable impact on the average observing
	efficiency for the mission - down to 61% compared to 65% in
	2004. As a result of the new thermal constraints, an
	increasing number of observations are now being split into
	multiple segments and scheduled with other observations or
	segments that help ensure a favorable overall thermal
	profile. The Flight Operations Team and the Science Operations
	Team are monitoring the thermal situation carefully and
	working to minimize the impact on the science return for the
	mission.
  
 
  The observing program transitioned from Cycle 6 to Cycle
    7 observations in December,
	although we expect a number of remaining Cycle 6 observations
	to be interleaved with Cycle 7 observations through the first
	quarter of the year. There were 7 schedule interruptions in
	the last year due to high levels of solar activity, resulting
	in an overall loss of about 3% of the scheduled observing
	time. The mission planning team responded efficiently to all
	the solar re-plans and minimized the science lost. Planners
	also responded quickly to the 13 Target Of Opportunity (TOO)
	observations that required schedule interruptions. Its
	exciting to see so many TOOs being requested following
      SWIFT’s launch in November
	2004.
     The
	spacecraft continued to operate well overall with no
      safe modes or major
	anomalies. Operational highlights included completing the
	earth eclipse seasons of summer 2005 and winter 2006 with
	nominal power and thermal performance, and passing through a
	lunar eclipse without incident on November 1.
 
    The Flight Operations Team was also busy developing a number of
      flight software patches designed to increase the safety and
      science efficiency of Chandra. A patch was created to provide the
	capability to transition to Normal Sun Mode following
	execution of the Science Instrument safing actions (SCS 107)
	in response to a high radiation event. The capability ensures
	a favorable thermal attitude in cases when stopping the
	command load would violate a propulsion line thermal
	constraint. A second patch increased the value of the Electron
	Proton Helium INstrument (EPHIN) E1300 channel threshold by a
	factor of two. The new value will reduce the number of false
	triggers of the science instrument safing sequence (SCS 107)
	during periods of puffed-up radiation belts, and when EPHIN is
	at high temperature. The change will also help with mission
	planning by relaxing a thermal constraint. A third patch
	modified SCS 107 to move the Science Instrument Module (SIM)
	only once when SCS 107 is executed, rather than twice. The
	previous implementation consisted of two moves, the first to
	an intermediate position to allow the HRC camera door to be
	closed, and a second to its final HRC-S position. Because the
	HRC door is no longer closed during SCS 107 runs, the extra
	movement could be eliminated, reducing the likelihood of
	excessive SIM motor heating.
 
   The science instruments also continued to operate well overall,
      with only a small number of minor anomalies that had little
      impact on the science return. ACIS experienced a recurrence of a
      latch-up of the threshold crossing plane circuit that affected
      one observation in July. The t-plane was cleared at the start of
      the following observation by commands that reset the ACIS Front
      End Processors. The reset commands are routinely included in the
      loads in anticipation of an occasional occurrence of this
      anomaly, the last having been in November 2001. ACIS also
      experienced an unexpected power-down of its Digital Electronics
      Assembly side-A.  This event was thought to be due to a single
      event upset.
     HRC experienced nominal operations with the exception of a brief
      episode of anomalous secondary telemetry in December. The
      anomalous data were seen in the engineering portion of the
      telemetry stream and had no impact on operations. No corruption
      of the X-ray event data was observed.
  
 
   A number of important changes to the Chandra Operations Control
      Center ground system took place last year, including the
      transition in July to a direct network link to JPL (previously
      all mission data and communications had been routed through the
      GSFC closed I/ONet), and the migration to a new version of the
      ground system hosted on the Linux operating system. The ground
      team worked hard to perform the required testing to ensure a
      seamless transition from the old IRIX operating system and
      Silicon Graphics hardware. The team also prepared carefully for
      the 2005 leap-second and all systems handled the extra second on
      December 31 without difficulty.
 
     The Science Data Processing team continued their excellent record
      for throughput of data, with the average time from observation
      to delivery of data reduced to less than 2 days. The Chandra
      archive holdings grew by 0.3 TB to 2.6 TB (compressed) during
      the year and now consists of 9.6 million files. A new mirror
      site for the archive was established at IUCAA in Pune,
      India.
 
     The Data System team released software updates in support of the
      Cycle 7 proposal submission deadline and Peer Review, and for
      the Cycle 8 Call for Proposals in December. Work has also
      continued on preparations for the third full re-processing of
      the Chandra archive.
 
     The Education and Public Outreach team was very active with 24
      press releases, a NASA Media Telecon and 10 additional image
      releases. The interest in the Chandra web site and educational
      products remained at near record levels last year.
     We
      look forward to continued smooth operations and exciting science
      results.
 
Roger Brissenden