See http://cxc.harvard.edu/mta/SOT_reports/sot-shift.html Shift Report L7026 Start at 2018:290:00:55 GMT = 8:55 October 16,2018 End at 2018:290:01:25 GMT = 9:25 pm October 16,2018 ACIS SOT Shift Report October 16 2018 ACIS Personnel: Dick Edgar, Paul Plucinsky, Catherine Grant PLAN -------- We ran CAP1463 to interrupt the ACIS CTI run currently in progress. script File executed: I_1_STANDBY_A.ssc SUMMARY: -------- The CAP executed exactly as expected. TIMELINE (GMT day 290) ---------------------- 290:00:57 AOS on DSS 65 290:00:58 ACIS focal plane temperature -114.7 C. 290:01:06 ACIS 1DPAMZT temperature 33.7 C. 290:01:17 Start script I_1_STANDBY_A.ssc 290:01:18 GO for execution of uplinked command loads 290:01:19 ACIS verifies good command echoes: two stop science, power down, sys config dump 290:01:25 ACIS verifies input currents and voltages. Note that the OC has also cleared SCS 135, which was still open from CAP 1462.